            EAC 1 Segment D Cable Fault

 

 

Fault Type:  

Cable Cut approximately 940 Km from Hong Kong CLS.

 

HD/PA Ticket:  

347099

 

Current Status:

Initial Splice and start spare cable payout to CB#1

 

Cable Ship:  

CS Durable

 

Cause:

Seismic Activity / Turbidity Slide

 

Comments:

HD#2 HKG end recovered. Initial Splice in progress

 

Estimated/Actual Traffic Switched:        20th Mar 1840hrs HKT

(N.B. “Estimated traffic Switched:” is stated for Protected SDH Traffic ONLY which has not already been affected by a Full Cable Fault. Unprotected and 10G wave service’s are not expected to experience an outage (Unless the fault is already a “Full Cable Fault”) until the “Cutting Cable” Activity.

 

Estimated Traffic Returned:                     4th Apr 18:00hrs HKT

(N.B. “Estimated traffic Return:” is stated for Protected SDH Traffic ONLY. Unprotected and 10G wave service’s may experience hits and random up & down periods from “Final Splice” onwards till the “Repair completion”. However, the services are considered stable and safe to use from the “Estimated traffic Return:” Date/Time onwards).

 

Est./Act Date

Step 

Activity

Status

29th Mar

Step 01

Transit to Cable Ground

Completed

29th Mar

Step 02

Arrive at the Cable Ground

Completed

30th Mar

Step 03

Preparation & Route Survey

Completed

31st Mar

Step 04

Cable Recovery

Completed

1st   Apr

Step 05

Splice Work (Initial & Final)

Ongoing

4th  Apr

Step 06

Repair Completion

Pending

 


 

    EAC 1 Segment C 2nd Cable Fault

 

 

Fault Type:  

Cable Cut approximately 1210 Km from Hong Kong CLS.

 

HD/PA Ticket:  

347123

 

Current Status:

Pending Seg D repair Completion

 

Cable Ship:  

CS Durable

 

Cause:

Seismic Activity / Turbidity Slide

 

Comments:

Pending Seg D repair Completion

                                         

Estimated/Actual Traffic Switched:        20th Mar 1934hrs HKT

(N.B. “Estimated traffic Switched:” is stated for Protected SDH Traffic ONLY which has not already been affected by a Full Cable Fault. Unprotected and 10G wave service’s are not expected to experience an outage (Unless the fault is already a “Full Cable Fault”) until the “Cutting Cable” Activity.

 

Estimated Traffic Returned:                     16th Apr 18:00hrs HKT

(N.B. “Estimated traffic Return:” is stated for Protected SDH Traffic ONLY. Unprotected and 10G wave service’s may experience hits and random up & down periods from “Final Splice” onwards till the “Repair completion”. However, the services are considered stable and safe to use from the “Estimated traffic Return:” Date/Time onwards).

 

Est./Act Date

Step 

Activity

Status

5th    Apr

Step 01

Transit to Cable Ground

Pending

6th    Apr

Step 02

Arrive at the Cable Ground

Pending

6th    Apr

Step 03

Preparation & Route Survey

Pending

6th    Apr

Step 04

Cable Recovery

Pending

11th Apr

Step 05

Splice Work (Initial & Final)

Pending

16th Apr

Step 06

Repair Completion

Pending


Pacnet will keep you posted on the repair progress. Please do not hesitate to contact Pacnet Planned Activity Group at pscpateam@pacnet.com if you have any questions or concerns about this notification. Your cooperation is greatly appreciated.

Regards

Jess Liew
Enterprise Support Executive
Pacnet Customer Service
pscpateam@pacnet.com    
International Dialing Number (IDD):+65 6419 2001

Toll Free Numbers:

Australia

1800-003-051

Indonesia

001-803-65-7632

New Zealand

0800-44-6215

Northern China

10800-650-0245

Ireland

1800-556-529

Philippines

1800-1651-0408

Southern China

10800-265-0245

Italy

800-785-325

Singapore

1800-419-2007

France

0800-919-870

Japan

0120-159-686

Taiwan

00801-65-1632

Germany

0800-181-2569

Korea

00798-651-7194

Thailand

001800-65-6430

Hong Kong

800-90-1500

Malaysia

1800-80-6029

UK

0800-917



Friday, April 1, 2011

« 返回